Home > Projects > Featured Project: Central Hall Westminster

Central Hall Westminster

Aims

Central Hall Westminster

Killby & Gayford was appointed to refurbish this London landmark in July 2004. The project aims to:

  • Refurbish the Great Hall including the installation of a rising stage.
  • Replace the ageing heating system.
  • Demolish an existing staircase to form a twin lift shaft to improve access and comply with DDA regulations.
  • Refurbish the administration offices and function rooms.

Project Team

  • Client: The Westminster Central Hall Management Committee
  • Architect: Richard Griffiths Architects
  • Quantity Surveyors: Sawyer & Fisher
  • Structural Engineer: Scott White & Hookins
  • Services Engineer: BJP Ltd.
  • Planning Supervisor: Moran Architects

Timeline

Central Hall Westminster: 12th April 2006

12th April 2006

  • Final completion of the Great Hall
  • Refurbishment of the adminsitrative offices and function rooms
  • Upgraded services and DDA compliance
Central Hall Westminster: 16th June 2005

16th June 2005

  • Installation of New sound Desk made by the K&G Joinery factory to control all speakers in the Great Hall
  • Laying of new carpet to the Great Hall and several corridors.
  • New disabled ramp built
  • Sanding and sealing of new stage and infilling non-slip patches
  • All works to the Great Hall had to be completed in time for a concert held for the Queen
Central Hall Westminster: 17th May 2005

17th May 2005

  • Commencement of marble and stone cleaning programme.
  • Ongoing installation and commissioning of new stage.
  • Continuation of door refurbishment and heating upgrade works.
  • Commencement of decoration works to Crush Hall.
Central Hall Westminster: 16th March 2005

16th March 2005

  • Installation of rising stage in the Great Hall
  • Replacement of exisiting balustrade in the Great Hall.
  • Commencement of decoration packages to rear corridors.
Central Hall Westminster: 16th February 2005

16th February 2005

  • Demonstration of new rising stage
  • Continuation of door refurbishment and heating upgrade works.
Central Hall Westminster: 22nd December 2004

22nd December 2004

  • Demolition of south staircase to make way for new lifts.
  • Continuation of door refurbishment and heating upgrade works.
Central Hall Westminster: 16th November 2004

16th November 2004

  • Installation of temporary protection to Great Hall whilst parquet flooring removed to prepare for new stage.
  • Start of door refurbishment programme to upgrade fire protection.
  • Works to upgrade heating system commenced.
Central Hall Westminster: 20th October 2004

20th October 2004

  • Completing rerouting of fire alarm system to begin demolitions.
  • Great Hall scaffolding erected for air tight enclosure prior to demolition of stage area.
  • Toilet refurbishment underway.
  • Boiler room strip out underway after asbestos removal.
Central Hall Westminster: 1st October 2004

1st October 2004

  • Scaffolding is being erected.
  • Partitions formed to restrict public access to works.
  • Temporary protection installed.
  • Asbestos removal underway from basement.
  • Boiler room stripped out.
Central Hall Westminster: 2nd August 2004

2nd August 2004

  • Project secured.
  • Pre-contract logistical planning underway.

Top of page